Skip to content
  1. Counties
  2. Marsabit County

Laisamis Constituency

Constituency code 048Registered voters 33,446

Laisamis Constituency covers the south of Marsabit County. It stretches from Loiyangalani on the eastern shore of Lake Turkana to Laisamis town. It was once known as Marsabit South. It has five wards: Loiyangalani, Kargi/South Horr, Korr/Ngurunit, Logologo and Laisamis.

It had 33,446 registered voters in 2022. Korr/Ngurunit was the largest ward with 9,392 voters. Joseph Lekuton of UDM is the MP. He first held the seat from 2006 to 2017 and returned in 2022.

Member of Parliament

MP
Joseph Lekuton
Joseph LekutonParliament of Kenya
Joseph Lekuton

UDM. Since Aug 2022

Elections

General election of 9 Aug 2022

SeatWinnerPartyVotesRunner-up
MPJoseph LekutonUDM6,127Marselino Malimo Arbelle, 5,856
Earlier general elections

8 Aug 2017

SeatWinnerPartyVotesRunner-up
MPMarselino Malimo ArbelleJP12,557, 59.3%Joseph Lekuton, 8,603, 40.7%

4 Mar 2013

SeatWinnerPartyVotesRunner-up
MPJoseph LekutonODM8,894, 51%David Lemeryan Timado, 3,031, 17.4%
President, votes hereRaila OdingaODM9,567, 54.8%Uhuru Kenyatta, 7,658, 43.9%

27 Dec 2007

SeatWinnerPartyVotesRunner-up
MPJoseph LekutonKANU10,001Abubakar G Harugura, 7,189

Results come from elections.co.ke, which links each figure to its source. All results for this place

About Laisamis Constituency

Laisamis covers the south and south west of Marsabit County. It takes in the Kaisut Desert and Mt Kulal and reaches the eastern shore of Lake Turkana at Loiyangalani. The 2019 census counted 101,089 people on 20,290.5 sq km. It has five wards: Loiyangalani, Kargi/South Horr, Korr/Ngurunit, Logologo and Laisamis. Loiyangalani and Laisamis are the main towns. Most of the constituency is dry grassland and bushed stone land. Fishing takes place at Loiyangalani on Lake Turkana. The constituency hosts the Lake Turkana Wind Power farm. It has 365 turbines and a capacity of 310MW. The company calls it Kenya's largest single private investment. The upper slopes of Mt Kulal and the Kamboe area get up to 1,000mm of rain and suit farming.

Economy and key figures

Lake Turkana Wind Power investment
EUR 625 million 2026
Population
101,089 2019
Population density
5 people per sq km 2019
Area
20,290.5 sq km 2024
Wards
5 2024
Locations and sub-locations
11 locations and 30 sub-locations 2024
Registered voters
33,446, up from 28,104 in 2017 2022
Loiyangalani town population
5,193 2019
Laisamis town population
5,047 2019
Constituency code
048 2023/24

What is grown here

3
Crop or productOutputYearWhere and notes
Crops50 acres put under crops in Laisamis sub-county2023/24Part of 4,200 acres put under crops county-wide
FishFresh fish handled by the Loiyangalani Fish Cooperative2023
Agro-pastoral landMiddle slopes of Mt Kulal and the Kamboe area2024The NG-CDF office says these areas support settled agro-pastoral farming

How people make a living

2
  • Wind power

    LTWP's 365 turbines of 850kW each give an installed capacity of 310MW. The farm began feeding the national grid on 24 Sep 2018.

  • Pastoralism

    The NG-CDF office says Kargi/South Horr, Laisamis, Loglogo and Korr-Ngurunit lie in the very dry zones of dwarf-shrub grassland and bushed stone land.

Budget and revenue

11
YearItemAmount
2026/27NG-CDF allocationKES 192.6 million
2025/26NG-CDF allocationKES 192.6 million
2024/25NG-CDF allocationKES 179.4 million
2023/24NG-CDF allocationKES 175.4 million
2022/23NG-CDF allocationKES 145.1 million
2013/14NG-CDF allocationKES 74.4 million
2023/24NG-CDF secondary school bursariesKES 45 million
2023/24NG-CDF tertiary bursariesKES 16.4 million
2023/24NG-CDF emergency reserveKES 9.2 million
2023/24Total of approved NG-CDF projectsKES 168 million
2025/26County ward road works planned for Laisamis sub-countyKES 9.5 million

Major projects and NG-CDF spending

13
  • Laisamis NG-CDF digital centre

    A digital centre at the NG-CDF office at Laisamis sub-county headquarters.

    2023/24, KES 5.2 million, Planned, NG-CDF

  • Ngurunit Secondary School dining hall

    A 100-capacity dining hall, kitchen and store with tables and benches.

    2023/24, KES 4.5 million, Planned, NG-CDF

  • Loglogo Girls Secondary School administration block

    An administration block with office furniture.

    2023/24, KES 4 million, Planned, NG-CDF

  • Loglogo Girls Secondary School dormitory renovation

    Renovation of four 100-student dormitories.

    2023/24, KES 3 million, Planned, NG-CDF

  • Kamboe Primary School renovation

    Renovation of eight classrooms.

    2023/24, KES 3.1 million, Planned, NG-CDF

  • Dakhane Primary School administration block

    An administration block with offices, a store and a staffroom plus furniture.

    2023/24, KES 2.8 million, Planned, NG-CDF

  • Korr Primary School administration block

    An administration block with offices, a store and a staffroom plus furniture.

    2023/24, KES 2.8 million, Planned, NG-CDF

  • Lontolio Primary School administration block

    An administration block with offices, a store and a staffroom plus furniture.

    2023/24, KES 2.8 million, Planned, NG-CDF

  • Laisamis Hospital upgrade

    Upgrading of Laisamis Hospital. The contract was awarded in 2023/24.

    2023/24, KES 15 million, Under way, County government

  • Loiyangalani fish processing factory

    A planned fish processing factory with solar-powered cold chain at Loiyangalani.

    2025/26, KES 50 million, Planned, County government and partners

  • Loiyangalani fish landing site

    A planned new landing site at Loiyangalani.

    2025/26, KES 35 million, Planned, County government and partners

  • Korr Energy Centre

    Equipping of the energy centre at Korr.

    2025/26, KES 4.8 million, Planned, County government

  • Civicon football pitch

    328 metres of chain-link fencing, gates and goalposts for a village pitch in Loiyangalani ward. It was handed over on 3 Oct 2026.

    2026, Complete, Lake Turkana Wind Power

Achievements

3
  • 2026

    LTWP upgraded more than 208 km of road from Laisamis to the wind farm. Travel between Sarima and Laisamis fell from 7 hours to 3 hours.

  • 2026

    The first 25 Winds of Change scholarship recipients from Laisamis constituency were awarded comprehensive scholarships in engineering and education.

  • 2020

    Kargi Police Line, Oljurot AP Line and Kulal Girls Secondary School were completed with NG-CDF funds in 2019/20.

Challenges

3
  • Insecurity

    LTWP says cattle rustling and competition for water drove conflict between communities. It reports cases have dropped since the project began.

  • Scarce water

    The NG-CDF office notes there are no permanent rivers in the county. Seasonal rivers such as the Milgis and Merille in the far south drain into the Sori Adio swamp.

  • Teacher retention

    A chief in Ngurunit said poor housing made it hard for teachers to stay at Mpagas Primary School until LTWP built staff units.

Standout institutions

4
  • Lake Turkana Wind Power

    Africa's largest wind farm by the company's own account, with 365 turbines and 310MW installed.

  • Kulal Girls Secondary School

    A girls' secondary school with completed NG-CDF works.

  • Laisamis Sub-County Hospital

    A sub-county hospital the CIDP plans to upgrade with a lab, maternity, wards, a theatre and a CT scan room.

  • Ngurunit Secondary School

    A secondary school approved for an NG-CDF dining hall in 2023/24.

Top businesses and employers

2

For investors

Opportunities

  • Fisheries

    The county plans a KSh 50 million fish factory and a KSh 35 million landing site at Loiyangalani with partners.

  • Skills and training

    LTWP chose engineering and teacher training for its scholarships after a job market study for Kenya and Marsabit.

  • Livestock products

    The county planned KSh 20 million in 2025/26 for livestock value addition. It covers a milk processing plant and honey and meat processing equipment in Moyale, North Horr, Laisamis and Saku.

How to set up

  1. Get a Single Business Permit from the county. Food, liquor and fish businesses also need a public health licence, a liquor licence or a fish trader's licence.
  2. Read the county Annual Development Plan and budget papers before bidding or investing. They list planned projects by sub-county and ward.

Roads, power and transport

  • A 438 km transmission line built by the government links the wind farm to the national grid.

  • Loiyangalani has an airstrip.

  • LTWP sells all its power to Kenya Power and does not distribute it. Power for nearby communities depends on Kenya Power, KETRACO and REA.

Who to contact

  • NG-CDF Laisamis office

    P.O. Box 71-60500 Marsabit. Phone 0720 108 050. Website laisamis.ngcdf.go.ke

  • Lake Turkana Wind Power

    P.O. Box 2114-00502, Karen, Nairobi. Website ltwp.co.ke

In the news

Loading stories

Wards (5)

  • Loiyangalani
  • Kargi/South Horr
  • Korr/Ngurunit
  • Logologo
  • Laisamis

Other constituencies in Marsabit County