Rural Electrification and Renewable Energy Corporation
Parastatal. Attached to a ministry, run by its own boardREREC carries out rural electrification projects across Kenya. The Energy Act 2019 added renewable energy to its mandate. It now leads the national green energy drive.
- Set up under
- Energy Act, 2019. REREC succeeded the Rural Electrification Authority.
- Website
- rerec.co.ke
- info@rerec.co.ke
- Phone
- +254 709 193000
- Office
- Kawi Complex, South C, Nairobi
- Postal address
- P.O. Box 34585-00100, Nairobi
- Social media
Leadership
Chief Executive Officer
Appointed by the Board of Directors
Rose MkalamaChief Executive Officer
Chairperson, Board of Directors
Godfrey LemisoChairperson, Board of Directors
General Manager, Corporate Services
Holder not published.
Past holders (1)
- Rose Mkalama Dates not published
General Manager, Energy Centres
Holder not published.
Past holders (1)
- Rose Mkalama Dates not published
General Manager, Information, Education and Communication
Holder not published.
Past holders (1)
About REREC
The Rural Electrification and Renewable Energy Corporation brings electricity to rural homes, schools, markets and health centres. It also leads government work on solar, biogas and clean cooking. It took over from the Rural Electrification Authority under the Energy Act 2019. In the 2024/25 financial year it raised KES 12.43 billion, most of it for development. It commissioned 889 grid projects, built 4,791.56 km of power lines and connected 75,944 new customers. It also runs 18 energy centres across the country. The Auditor-General gave a qualified opinion on its 2024/25 accounts over KES 1.6 billion paid for land surveys that the police are investigating. Its head office is at Kawi Complex in South C, Nairobi.
Key figures
- Grid projects commissioned
- 889 2024/25 libraryir.parliament.go.ke
- Public facility projects commissioned
- 481 2024/25 libraryir.parliament.go.ke
- Transformer projects commissioned
- 408 2024/25 libraryir.parliament.go.ke
- New customers connected
- 75,944 2024/25 libraryir.parliament.go.ke
- Power lines built
- 4,791.56 km 2024/25 libraryir.parliament.go.ke
- Energy centres
- 18 2026